Force Majeure and Hardship under German Law: § 313 BGB and Contract Clauses

Force majeure is not defined in the German Civil Code. Instead, German law deals with unforeseen events through the rules on impossibility, fault-based liability and the doctrine of disturbance of the basis of the contract in § 313 BGB. Contract clauses can fill the gaps, but they must be drafted with these statutory rules in mind. Pandemic closures, energy price shocks, sanctions and supply chain disruptions have shown how important well-designed clauses are.

Container port disruption raising force majeure questions under German law

Key takeaways

  • A debtor is released from performance where it is impossible (§ 275(1) BGB) and may refuse performance in cases of gross disproportion (§ 275(2) BGB).
  • Damages require fault: there is no liability if the debtor is not responsible for the breach (§ 280(1) BGB).
  • If the basis of the contract changes fundamentally, a party can demand adjustment and, as a last resort, withdraw or terminate (§ 313 BGB).
  • Courts apply § 313 BGB restrictively and give priority to the contractual risk allocation.
  • A temporary statutory presumption for commercial leases during the pandemic (Article 240 § 7 EGBGB) has since been repealed.

No statutory force majeure rule

Many international contracts contain a force majeure clause, and many business people assume that the law provides a general defence of this kind. German law does not. The Civil Code (BGB) contains no general definition or rule on it. The term appears only in specific statutes, such as transport and travel law. Instead, three sets of general rules address unforeseen events: the rules on impossibility of performance, the requirement of fault for damages claims, and the doctrine of disturbance of the basis of the contract (Störung der Geschäftsgrundlage) in § 313 BGB.

Container port disruption raising force majeure questions under German law
Supply chain disruptions test contract clauses and § 313 BGB.

A contractual force majeure clause therefore does not merely restate the law; it changes the statutory allocation of risks. That makes it important to understand the statutory baseline before drafting or invoking a clause. German courts interpret contractual clauses in light of the statutory rules and, where clauses are standard terms, review them under §§ 305 to 310 BGB.

This article explains the statutory rules, the requirements of § 313 BGB, the design of contractual clauses, and lessons from recent crises.

Impossibility and fault

Under § 275(1) BGB, the claim to performance is excluded to the extent that performance is impossible for the debtor or for anyone. A debtor may also refuse performance if it requires effort that is grossly disproportionate to the creditor's interest in performance, taking into account the content of the obligation and good faith (§ 275(2) BGB). If the debtor need not perform, the creditor generally loses its obligation to provide counter-performance (§ 326(1) BGB).

Whether the debtor must pay damages is a separate question. Under § 280(1) BGB, the creditor can claim damages for a breach of duty unless the debtor is not responsible for it. The debtor is responsible for intent and negligence unless a stricter or milder liability is agreed, for example by assuming a guarantee or a procurement risk (§ 276(1) BGB).

An event beyond the debtor's control – a natural disaster, a government ban, a strike at a third party – usually means the debtor is not at fault. However, a seller of generic goods who has assumed a procurement risk may be liable even without fault if the goods are still available on the market.

Legal instrumentEffectProvision
ImpossibilityRelease from the duty to perform; loss of counter-performance§§ 275(1), 326(1) BGB
Gross disproportionRight to refuse performance§ 275(2) BGB
No faultNo damages for breach§ 280(1) BGB
Disturbance of the basis of the contractAdjustment; withdrawal or termination as last resort§ 313 BGB
Termination for good causeTermination of long-term contracts§ 314 BGB

Temporary impediments

Many disruptive events are temporary: a port closure, a factory fire, a cyber attack. German law treats temporary impossibility mainly through the rules on delay. The debtor is not in default if it is not responsible for the delay. If the delay makes the purpose of the contract unachievable or continued waiting unreasonable, it may be treated as permanent impossibility. Contracts should regulate temporary impediments specifically, including suspension periods and termination rights.

Disturbance of the basis of the contract (§ 313 BGB)

Under § 313(1) BGB, if circumstances that became the basis of the contract have changed significantly after conclusion, and the parties would not have concluded the contract or would have concluded it with different content had they foreseen the change, adjustment of the contract can be demanded to the extent that one party cannot reasonably be expected to uphold the unchanged contract, taking into account all circumstances, in particular the contractual or statutory allocation of risks. If adjustment is impossible or unreasonable, the disadvantaged party can withdraw or, for long-term contracts, terminate (§ 313(3) BGB).

The doctrine is a safety valve, not a general escape clause. Courts apply it restrictively. Above all, it does not apply where the contract or the law allocates the risk to one party. A party that agreed a fixed price bears the risk of cost increases; a supplier that assumed a procurement risk bears the risk of supply shortages. Only when a change goes far beyond the risks assumed and leads to an intolerable result can § 313 BGB help. Even then, the primary remedy is adjustment, for example a price increase or a sharing of losses, not termination.

Pandemic and energy crisis

The COVID-19 pandemic tested § 313 BGB in practice. For commercial leases, the legislature introduced a temporary presumption that government closure orders could constitute a significant change of the basis of the contract (Article 240 § 7 EGBGB), which has since been repealed. The Federal Court of Justice confirmed that pandemic-related closures could justify a rent adjustment, but rejected a schematic split of losses and required an assessment of all circumstances of the individual case. During the energy crisis of 2022, many suppliers and customers relied on § 313 BGB for price adjustments, with mixed results depending on the contractual risk allocation.

Designing force majeure clauses

A good force majeure clause defines the triggering events, the required causal link, the notice and mitigation duties, the legal consequences and the termination rights. Definitions commonly combine a general description – an event beyond the party's reasonable control that could not reasonably have been foreseen or avoided – with a non-exhaustive list of examples such as natural disasters, epidemics, war, terrorism, sanctions, government measures, strikes and cyber attacks. Whether events at suppliers or subcontractors count should be addressed expressly.

Legal consequences usually include suspension of the affected obligations for the duration of the event, exclusion of damages, and a right to terminate if the event lasts longer than a defined period. The clause should clarify whether the affected party remains obliged to make payments and how partial performance and allocation of limited supplies (for example pro rata among customers) are handled. Many companies use the ICC model clause as a starting point and adapt it to German law.

Practical point

Review force majeure clauses against the actual risks of your supply chain. A clause that lists "epidemics" but not "government measures", or that excludes events at sub-suppliers, may fail exactly when it is needed. Notice requirements should be practical and deadlines realistic.

Standard terms control

Such clauses in standard terms are reviewed under § 307 BGB. A clause that allows the user to escape its obligations too easily, for example on the basis of any delivery problem at a supplier, may be invalid as an unreasonable disadvantage. Our article on standard terms in B2B contracts explains the test.

Hardship and price adjustment clauses

The clauses discussed above address events that prevent performance. Hardship clauses address events that make performance much more onerous without preventing it, such as sharp cost increases. They typically oblige the parties to renegotiate in good faith if circumstances change fundamentally and provide for a mechanism if negotiations fail, such as adjustment by an expert or a court, or termination.

Because § 313 BGB is restrictive, a contractual hardship clause can give more predictability. The clause should define the threshold for hardship as precisely as possible, for example by reference to a percentage increase in specified costs, and set a timetable for negotiations so that the parties are not left in limbo.

In many cases, a price adjustment clause linked to objective indices – energy prices, raw material indices, wage indices – is more practical than a general hardship clause. Such clauses must be transparent and, in standard terms, balanced: they must allow price reductions as well as increases and must not allow the user to increase its profit margin. Our article on limitation of liability clauses discusses related drafting issues.

Sanctions, export controls and tariffs

Recent years have added new types of disruption: sanctions against Russia and Belarus, export control restrictions on dual-use goods and sudden tariff increases. Sanctions can make performance legally impossible; a party that is prohibited from delivering under EU sanctions law cannot be ordered to perform, and EU sanctions regulations contain no-claims clauses protecting parties that do not perform because of sanctions. Export licence requirements can delay performance, and licence refusals can make it impossible.

Tariffs, by contrast, usually make performance more expensive rather than impossible. Whether the seller or the buyer bears the cost depends on the agreed delivery terms, such as Incoterms, and on price clauses. Only exceptionally will tariff increases justify adjustment under § 313 BGB. Contracts should therefore contain specific sanctions, export control and tariff clauses rather than relying on general force majeure language. Our article on US tariffs and contracts discusses these issues.

Practical steps when an event occurs

When an event affects performance, companies should first analyse the contract: is there a force majeure or hardship clause, what does it cover, what are the notice requirements? They should then assess the statutory position under §§ 275, 280 and 313 BGB. Notice should be given promptly and in the required form, with a description of the event, its expected duration and its effect on performance. Mitigation efforts – alternative suppliers, alternative routes, partial deliveries – should be documented, since they matter for fault and for the reasonableness of claims.

Where the event affects many contracts, a coordinated approach across customers and suppliers is essential. Companies should avoid inconsistent positions, such as invoking an excuse towards customers while insisting on full performance by their own suppliers for the same event. Correspondence should be drafted carefully, as it will become evidence in later disputes.

Insurance cover should also be checked early. Business interruption, contingent business interruption and trade credit policies may respond to certain events, but they often contain exclusions, for example for epidemics or war, and strict notification deadlines. Coordinating the contractual position with insurance claims helps to avoid a situation in which a company waives contractual claims that its insurer would expect it to pursue.

International contracts

Where the UN Convention on Contracts for the International Sale of Goods applies, Article 79 CISG exempts a party from damages if the failure was due to an impediment beyond its control that it could not reasonably have been expected to take into account or overcome. Its relationship with contractual clauses and with German domestic law should be considered when drafting cross-border supply contracts.

How TRW & Co helps with force majeure and hardship

We advise companies on excuse, hardship and price adjustment clauses and on the application of §§ 275, 280 and 313 BGB in crises. We review and draft clauses, assess claims and defences when supply chains are disrupted, prepare notices and negotiate contract adjustments, and represent clients in litigation and arbitration. Our work connects with our commercial contracts, commercial litigation and manufacturing teams. Please contact us. This article is general information and not legal advice.

Frequently asked questions

Does German law have a statutory force majeure rule?

No. The BGB contains no general force majeure provision. Unforeseen events are handled through impossibility (§ 275 BGB), the fault requirement for damages (§ 280 BGB) and the disturbance of the basis of the contract (§ 313 BGB). Contract clauses can modify this allocation.

When can a contract be adjusted under § 313 BGB?

If circumstances forming the basis of the contract change significantly, the parties would not have contracted on those terms, and one party cannot reasonably be expected to uphold the unchanged contract, considering especially the contractual and statutory risk allocation. Courts apply this restrictively.

Is a supplier liable if it cannot deliver due to a disaster?

Generally not for damages, if it is not at fault (§ 280(1) BGB). But if it assumed a procurement risk or a guarantee, it may be liable without fault. Its claim to payment usually lapses if it does not perform (§ 326 BGB).

What should a force majeure clause contain?

A definition with examples, the causal link required, notice and mitigation duties, consequences such as suspension and exclusion of damages, rules on payment and allocation of limited supplies, and a termination right if the event lasts too long.

How did courts handle pandemic rent claims?

A temporary presumption in Article 240 § 7 EGBGB, since repealed, applied to commercial leases. The Federal Court of Justice accepted that closures could justify adjustment under § 313 BGB but required an individual assessment rather than a fixed split.

Sources

  1. § 275 BGB – Exclusion of the duty to perform (gesetze-im-internet.de)
  2. § 280 BGB – Damages for breach of duty (gesetze-im-internet.de)
  3. § 313 BGB – Disturbance of the basis of the contract (gesetze-im-internet.de)
  4. § 314 BGB – Termination for good cause (gesetze-im-internet.de)

General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.